Cafeteria Roof & A/C Project Status

June 29, 2021
New Weekly Latin Mass, Tuesdays at 5:30 pm
August 25, 2021

√ During the week of November 1, 2021, asbestos abatement of the meeting room’s flooring was successfully completed.

√ Facilities Service Manager Eric LeDuff worked October 11-14, 2021, to secure a tarp on the roof of the cafeteria to prevent more water from leaking into the structure and further damaging the walls while we await the construction of the new roof.

AST Engineers, ANR Construction, and WHLC Architects, with whom we have contracted, informed us that the start date for construction has shifted to April 2022, due to the global delay in the delivery of building materials.

√ As of September 27, 2021, $122,593.46 has been donated toward the new roof and HVAC system since July 1, 2021. This means any additional money donated before June 30, 2022 will be kept 100% by the parish—none of it will be taxed by the diocese. Thank you to everyone for your past and ongoing generosity!

√ All contracts and financing were approved in July 2021 for construction to move forward.